September 4 learned from the civil aviation sector, Yushu Sanjiangyuan Airport after nearly four months of the construction, the airport has taken shape, the quality of all qualified.
Yushu Sanjiangyuan airport since May 16 has been started, after the constructors day and night construction, the airfield runway and terminal area is clear and discernible contours, the airport has taken shape. As of August 25, has completed the excavation of 93%, completed the filling of 90% over the 20 days ahead of the contract deadline. After supervision, the Sanjiangyuan airport project quality indicators qualified, meet or exceed the aviation industry standards.
The airport is located in Yushu Sanjiangyuan alpine zone, the average altitude of 3,950 meters, altitude hypoxia, climate change, for the quality of this year's scheduled completion of construction tasks, construction site machinery, equipment round-the-clock construction, engineering peaked, large machinery amounted to 422 units, nearly constructers 1200. It is known that since the start of the airport building, more than 50 constructors are not suited to the local climate and safety away from, not present any personnel casualties at present.
Moreover, in accordance with "to build the Yushu Airport into a green airport" requirements, the Airport Group construction company and the construction unit to concentrate on garbage collection, focus is now on the turf 38 Wanfang transplantation restored the soil surface and covered with. (Author: Zhao Linsong)
Editor: Carolyn
|